RERA projects in Wanjara
2 projects under 2 MahaRERA registrations, registered 2023–2024. 100% have a completion date extended beyond the one promised.
Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
8 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
10Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2023 | 1 |
| 2024 | 1 |
Projects in Wanjara
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Karan Kothari Business Park Shopping VillageKaran Kothari Business Park Private Limited | P50500055653 | 5 Apr 2024 | 15 Oct 2027 | 15 Feb 2028 | Extended 4 mo | 0 |
| Swapna-Niketan by NMCSandeep Dwellers Pvt. Ltd. | P50500050570 | 21 Apr 2023 | 31 Mar 2025 | 30 Mar 2026 | Extended 12 mo | 0 |
Other localities in Nagpur (Rural)
Most active promoters
By projects registered here, as named on MahaRERA.
- Karan Kothari Business Park Private Limited1 project
- Sandeep Dwellers Pvt. Ltd.1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology