Skip to content

Sumukh Enclave

Deedo IDDP-NGP-9QMQ

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record.

Shankarpur, Nagpur 441108 · by Aa Developers

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 16 Jun 2025, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50500080523
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050008052316 Jun 202531 Dec 202730 Apr 2028Aa DevelopersProject page
Documents76

27 documents held by Deedo, 49 filings listed on MahaRERA's project page

Registration certificate

Other (10)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
Show all 76 documentsShow fewer documents

Other (10)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView

Commencement certificate (4)

  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView

Form 1 (4)

  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView

Allotment letter

  • Allotment letterDate not statedView

Title report

  • Title reportDate not statedView

Encumbrance details

  • Encumbrance detailsDate not statedView

Layout plan (2)

  • Layout planDate not statedView
  • Layout planDate not statedView

Form B (3)

  • Form BDate not statedView
  • Form BDate not statedView
  • Form BDate not statedView

Finance

  • PAN CardAA Developer PAN.pdf · uploaded 10 Apr 2025View

Legal

  • Other – Legalshankarpur sale deed_compressed.pdf · uploaded 2 Jun 2025View
  • Other – Legal7-12-SHANKARPUR 47.PDF · uploaded 2 Jun 2025View
  • Legal Title reportTITLE REPORT WITH ANNEXURE.pdf · uploaded 4 Jun 2025View
  • Declaration Form B1 Declaration in FORM B (2).pdf · uploaded 11 Jun 2025View

Migrated

  • 1 PAN CardAA Developer PAN.pdf · uploaded 10 Apr 2025View
  • 1 a Details of encumbrances concerned to FinanceENCUMBRANCE.pdf · uploaded 10 Apr 2025View
  • 1 Copy of Layout Approval (in case of layout)SANCTION PLAN.pdf · uploaded 10 Apr 2025View
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 10 Apr 2025View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 10 Apr 2025View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 10 Apr 2025View
  • 1 Commencement Certificates / NA Order for plotted developmentNMRDA APPROVAL FINAL.pdf · uploaded 10 Apr 2025View
  • 1 Building Plan Approval / NA Order for plotted developmentNMRDA APPROVAL FINAL.pdf · uploaded 10 Apr 2025View
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT 'A'.pdf · uploaded 10 Apr 2025View
  • 1 Deviation Report with respect to Allotment letterdeviation allotment.pdf · uploaded 10 Apr 2025View
  • 1 b Details of encumbrances concerned to LegalENCUMBRANCE.pdf · uploaded 10 Apr 2025View
  • 1 Other – TechnicalANNEXURE A DECLARATION CUM UNDERTAKING.pdf · uploaded 10 Apr 2025View
  • 1 Deviation Report with respect to model copy of Agreementdeviation ats.pdf · uploaded 10 Apr 2025View
  • 1 Disclosure for secured/unsecured finance availed for the projectDISCLOSURE sec.pdf · uploaded 10 Apr 2025View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 AA developer.pdf · uploaded 2 Jun 2025View
  • 1 Other – Legalshankarpur sale deed_compressed.pdf · uploaded 2 Jun 2025View
  • 2 Other – Legal7-12-SHANKARPUR 47.PDF · uploaded 2 Jun 2025View
  • 1 CERSAI detailsSELF DECLARATION FOR NO CERSAI REPORT.pdf · uploaded 2 Jun 2025View
  • 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 2 Jun 2025View
  • 2 Disclosure of Interest in Other Real Estate Organizationsinterest in oth org.pdf · uploaded 2 Jun 2025View
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Project bank account(Shankarpur).pdf · uploaded 2 Jun 2025View
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 3 Jun 2025View
  • 1 Copy of the legal title reportTITLE REPORT WITH ANNEXURE.pdf · uploaded 4 Jun 2025View
  • 1 Declaration in FORM B1 Declaration in FORM B (2).pdf · uploaded 11 Jun 2025View
  • 2 Commencement Certificates / NA Order for plotted developmentAA DEVELOPERS2.pdf · uploaded 11 Jun 2025View
  • 3 Commencement Certificates / NA Order for plotted developmentAA DEVELOPER1.pdf · uploaded 11 Jun 2025View
  • 1 Proforma of Agreement for saleAGMT FOR SALE AA DEVELOPERS.pdf · uploaded 11 Jun 2025View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 20 Oct 2025View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 20 Oct 2025View
  • Withdrawal Update Form 3form 3 AA developer.pdf · uploaded 20 Oct 2025View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 20 Feb 2026View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 20 Feb 2026View
  • Withdrawal Update Form 3form 3 AA developer.pdf · uploaded 20 Feb 2026View
  • Withdrawal Update Form 1Form1 mar 26.pdf · uploaded 11 Jun 2026Source
  • Withdrawal Update Form 2Form 2 mar 26.pdf · uploaded 11 Jun 2026Source
  • Withdrawal Update Form 3Form 3 mar 26.pdf · uploaded 11 Jun 2026Source
  • Withdrawal Update Form 1Form1 mar 26.pdf · uploaded 21 Aug 2026Source
  • Withdrawal Update Form 2Form 2 mar 26.pdf · uploaded 21 Aug 2026Source
  • Withdrawal Update Form 3Form 3 mar 26.pdf · uploaded 21 Aug 2026Source

Technical

  • DocumentSANCTION PLAN.pdf · uploaded 10 Apr 2025View
  • DocumentNMRDA APPROVAL FINAL.pdf · uploaded 10 Apr 2025View
  • Other – TechnicalANNEXURE A DECLARATION CUM UNDERTAKING.pdf · uploaded 10 Apr 2025View

Technical (Architect)

  • DocumentForm1 mar 26.pdf · uploaded 11 Jun 2026Source

Technical (Engineer)

  • DocumentForm 2 mar 26.pdf · uploaded 11 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Kh no 47, P.H. No. 42

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
Kh no 47, P.H. No. 42, Mouza Shankarpur, Kh No 47, ShankarpurPIN 441108
Village
Shankarpur, Nagpur (Rural) taluka
Land area for this project
8,877 sq m (95,554 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
1,256 sq m (13,515 sq ft)
Designated bank account
119
Developed in phases
No

Survey, CTS, gat or plot numbers

Kh no 47P.H. No. 42

Land as published on MahaRERA's project page

Kh no 47, P.H. No. 42, Mouza Shankarpur

Boundaries

North
Kh no 123
South
Kh no 48
East
Kh No 46
West
Kh no 51

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRavindrasingh Janewar—
Chartered accountantCa Aditya Gautam—
EngineerRavindrasingh Janewar E 15 Sai Nagar Nagpur440027 8793779299—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Shankarpur

All 58 projects in Shankarpur · Compare Sumukh Enclave with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology