Deedo IDDP-NGP-9QMQCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record.
Shankarpur, Nagpur 441108 · by Aa Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 16 Jun 2025, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500080523
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500080523 | 16 Jun 2025 | 31 Dec 2027 | 30 Apr 2028 | Aa Developers | Project page |
Documents76
27 documents held by Deedo, 49 filings listed on MahaRERA's project page
Show all 76 documentsShow fewer documents
Commencement certificate (4)
Form 1 (4)
Allotment letter
- Allotment letterDate not statedView
Title report
- Title reportDate not statedView
Encumbrance details
- Encumbrance detailsDate not statedView
Finance
- PAN CardAA Developer PAN.pdf · uploaded 10 Apr 2025View
Legal
Migrated
- 1 PAN CardAA Developer PAN.pdf · uploaded 10 Apr 2025View
- 1 a Details of encumbrances concerned to FinanceENCUMBRANCE.pdf · uploaded 10 Apr 2025View
- 1 Copy of Layout Approval (in case of layout)SANCTION PLAN.pdf · uploaded 10 Apr 2025View
- 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 10 Apr 2025View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 10 Apr 2025View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 10 Apr 2025View
- 1 Commencement Certificates / NA Order for plotted developmentNMRDA APPROVAL FINAL.pdf · uploaded 10 Apr 2025View
- 1 Building Plan Approval / NA Order for plotted developmentNMRDA APPROVAL FINAL.pdf · uploaded 10 Apr 2025View
- 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT 'A'.pdf · uploaded 10 Apr 2025View
- 1 Deviation Report with respect to Allotment letterdeviation allotment.pdf · uploaded 10 Apr 2025View
- 1 b Details of encumbrances concerned to LegalENCUMBRANCE.pdf · uploaded 10 Apr 2025View
- 1 Other – TechnicalANNEXURE A DECLARATION CUM UNDERTAKING.pdf · uploaded 10 Apr 2025View
- 1 Deviation Report with respect to model copy of Agreementdeviation ats.pdf · uploaded 10 Apr 2025View
- 1 Disclosure for secured/unsecured finance availed for the projectDISCLOSURE sec.pdf · uploaded 10 Apr 2025View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 AA developer.pdf · uploaded 2 Jun 2025View
- 1 Other – Legalshankarpur sale deed_compressed.pdf · uploaded 2 Jun 2025View
- 2 Other – Legal7-12-SHANKARPUR 47.PDF · uploaded 2 Jun 2025View
- 1 CERSAI detailsSELF DECLARATION FOR NO CERSAI REPORT.pdf · uploaded 2 Jun 2025View
- 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 2 Jun 2025View
- 2 Disclosure of Interest in Other Real Estate Organizationsinterest in oth org.pdf · uploaded 2 Jun 2025View
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Project bank account(Shankarpur).pdf · uploaded 2 Jun 2025View
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 3 Jun 2025View
- 1 Copy of the legal title reportTITLE REPORT WITH ANNEXURE.pdf · uploaded 4 Jun 2025View
- 1 Declaration in FORM B1 Declaration in FORM B (2).pdf · uploaded 11 Jun 2025View
- 2 Commencement Certificates / NA Order for plotted developmentAA DEVELOPERS2.pdf · uploaded 11 Jun 2025View
- 3 Commencement Certificates / NA Order for plotted developmentAA DEVELOPER1.pdf · uploaded 11 Jun 2025View
- 1 Proforma of Agreement for saleAGMT FOR SALE AA DEVELOPERS.pdf · uploaded 11 Jun 2025View
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Oct 2025View
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Oct 2025View
- Withdrawal Update Form 3form 3 AA developer.pdf · uploaded 20 Oct 2025View
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Feb 2026View
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Feb 2026View
- Withdrawal Update Form 3form 3 AA developer.pdf · uploaded 20 Feb 2026View
- Withdrawal Update Form 1Form1 mar 26.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 2Form 2 mar 26.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 3Form 3 mar 26.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 1Form1 mar 26.pdf · uploaded 21 Aug 2026Source
- Withdrawal Update Form 2Form 2 mar 26.pdf · uploaded 21 Aug 2026Source
- Withdrawal Update Form 3Form 3 mar 26.pdf · uploaded 21 Aug 2026Source
Technical
Technical (Architect)
- DocumentForm1 mar 26.pdf · uploaded 11 Jun 2026Source
Technical (Engineer)
- DocumentForm 2 mar 26.pdf · uploaded 11 Jun 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Kh no 47, P.H. No. 42
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Kh no 47, P.H. No. 42, Mouza Shankarpur, Kh No 47, ShankarpurPIN 441108
- Village
- Shankarpur, Nagpur (Rural) taluka
- Land area for this project
- 8,877 sq m (95,554 sq ft)
- Permissible built-up area
- 0 sq m (0 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 1,256 sq m (13,515 sq ft)
- Designated bank account
- 119
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Kh no 47, P.H. No. 42, Mouza Shankarpur
Boundaries
- North
- Kh no 123
- South
- Kh no 48
- East
- Kh No 46
- West
- Kh no 51
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ravindrasingh Janewar | — |
| Chartered accountant | Ca Aditya Gautam | — |
| Engineer | Ravindrasingh Janewar E 15 Sai Nagar Nagpur440027 8793779299 | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Shankarpur
- Mauli Crystal-35RERA PP1190002600283
- Moreshwar Park 13RERA PP1190002501874
- Meerai Mahalaxmi Nagar 43RERA P50500081053
- Kelzare Nagari-IIRERA PP1190002400087
- Leverage Green MeadowsRERA P50500077369
- Mandwe LayoutRERA P50500054821
- Silver Park-14RERA P50500054108
- Dwarka Nagari 9RERA P50500053228
All 58 projects in Shankarpur · Compare Sumukh Enclave with another project