RERA projects in Parsodi (535883)
2 projects under 2 MahaRERA registrations, registered 2019–2023. None has an extended completion date on record.
2RERA projects
2Registrations
1Completion still due1 past their completion date, 1 marked completed
—Median extension beyond promised date0% of registrations extended
1Regulatory caseson 1 project
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
Projects in Parsodi (535883)
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shreekrishna PrideShree Krishna Infraventures | P50500051319 | 8 Jun 2023 | 31 Mar 2027 | — | Not yet due | 1 |
| AnandamAyodhya Commerce Pvt Ltd | P50500019831 | 5 Mar 2019 | 1 Feb 2023 | — | Completed | 0 |
Other localities in Nagpur (Rural)
- Jamtha93 projects
- Pipla83 projects
- Shankarpur51 projects
- Beltarodi38 projects
- Wela Harichandra36 projects
- Gotal Panjari34 projects
- Godhani (Railway)30 projects
- Besa29 projects
- Panjari Farm24 projects
- Bokhara21 projects
- Butibori17 projects
- Gawasi Manapur16 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Ayodhya Commerce Pvt Ltd1 project
- Shree Krishna Infraventures1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology