Skip to content

RERA projects in Khasarmari

1 project under 1 MahaRERA registration, registered 2023–2023. None has an extended completion date on record.

Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20231

Projects in Khasarmari

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Emzar HightownThe Squarefeet CompanyP505000493457 Feb 202331 Dec 202531 Dec 2025Promised date passed1

Other localities in Nagpur (Rural)

Most active promoters

By projects registered here, as named on MahaRERA.

  1. The Squarefeet Company1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology