3 projects under 3 MahaRERA registrations, registered 2018–2025. 33% have a completion date extended beyond the one promised.

3RERA projects
3Registrations
2Completion still due1 past their completion date, 3 marked completed
54 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181
20190
20200
20210
20220
20231
20240
20251

Projects in Dongargaon (535897)

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Rajatbhoomi - 13Tirupati DevelopersP5050007936228 Feb 202531 Dec 2029—Completed0
Dongargaon Commercial HubSonali Pankaj WaghmareP5050005109029 May 202331 Dec 2026—Completed0
Rajatbhoomi 1Tirupati DevelopersP5050001858821 Nov 201830 Sep 202031 Mar 2025Completed0

Other localities in Nagpur (Rural)

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Tirupati Developers2 projects
  2. Sonali Pankaj Waghmare1 project