RERA projects in Bahadura
7 projects under 7 MahaRERA registrations, registered 2017–2025. None has an extended completion date on record.
7RERA projects
7Registrations
2Completion still due5 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 2 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Bahadura
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aakriti HeightsRohini Nikhil Gulhane | P50500080648 | 23 Jun 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Arik ParkGanesh Jaganji Pardhi | P50500053609 | 10 Nov 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Saraswa CitySaraswa Infratech | P50500048661 | 12 Jan 2023 | 10 Oct 2024 | — | Promised date passed | 0 |
| Radha NagriHatwar Associates | P50500048040 | 7 Dec 2022 | 2 Sep 2025 | — | Promised date passed | 0 |
| Neelkanth NagarNayak Brothers | P50500032913 | 2 Feb 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Aakar HeightsAakar Constructions Group | P50500019717 | 22 Feb 2019 | 30 Mar 2025 | — | Promised date passed | 0 |
| Anand Vishwa BamboovanAnand Vishwa | P50500008821 | 19 Aug 2017 | 29 Jun 2023 | — | Promised date passed | 0 |
Other localities in Nagpur (Rural)
- Jamtha93 projects
- Pipla83 projects
- Shankarpur51 projects
- Beltarodi38 projects
- Wela Harichandra36 projects
- Gotal Panjari34 projects
- Godhani (Railway)30 projects
- Besa29 projects
- Panjari Farm24 projects
- Bokhara21 projects
- Butibori17 projects
- Gawasi Manapur16 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Aakar Constructions Group1 project
- Anand Vishwa1 project
- Ganesh Jaganji Pardhi1 project
- Hatwar Associates1 project
- Nayak Brothers1 project
- Rohini Nikhil Gulhane1 project
- Saraswa Infratech1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology