Ajani, Nagpur
7 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects3
Registrations3
Completion still due21 past their date
Median extension4 months67% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Ajani
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shubh Laxmi RealtorsShubh Laxmi Realtors | PP1190002600448 | 17 May 2026 | 31 Mar 2031 | 31 Jul 2031 | Extended 4 mo | 0 |
| Naidu ApartmentAnantram Ramdas Naidu | P50500033184 | 9 Feb 2022 | 31 Oct 2023 | 31 Oct 2023 | Promised date passed | 0 |
| Palm ValleyShri Balaji Land Developers | P50500021844 | 1 Aug 2019 | 29 Dec 2026 | 29 Apr 2027 | Extended 4 mo | 0 |
Nearby: other localities in Kamptee
Most active promoters
- Anantram Ramdas Naidu1 project
- Shri Balaji Land Developers1 project
- Shubh Laxmi Realtors1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology