RERA projects in Bhiwandi

447 projects under 485 MahaRERA registrations, registered 2017–2026. 53% have a completion date extended beyond the one promised.

Taluka
447RERA projects
485Registrationssome projects hold several
276Completion still due164 past their completion date, 3 marked completed
4 monthsMedian extension beyond promised date53% of registrations extended
34Regulatory caseson 16 projects
975Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201783
201836
201936
202016
202125
202260
202354
202441
202550
202639

Projects in Bhiwandi

447 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Ckp Builder And DeveloperCkp Builder And DeveloperPR13300026022209 Oct 202631 Dec 2029—Not yet due0
Shree Siddhivinayak BuildconShree Siddhivinayak BuildconPM13300026022479 Oct 202631 Dec 203031 Dec 2030Not yet due0
Maruti Complex MixedM/S. Maruti Poshamallu GalipelliPM13300026022038 Oct 202631 Dec 203031 Dec 2030Not yet due0
Paradise HeightFarhan Ayaz ShaikhPR13300026022118 Oct 202631 Dec 203031 Dec 2030Not yet due0
Kohinoor Uptown T1 & T6Kgi Realty Private LimitedPR13320226021285 Oct 202631 Mar 203031 Mar 2030Not yet due0
Pearl AvenueAl Araaf Infra Private LimitedPM133000260197321 Sep 202631 Mar 203131 Mar 2031Not yet due0
Metro HeightsBhakti RealtorsPR133000260193816 Sep 202631 Dec 2028—Not yet due0
Gangotri HeightsLaxmi ConstructionPR133000260192915 Sep 202630 Jun 202730 Jun 2027Not yet due0
Jai Malhar ResidencyJai Malhar BuildersPR133101260186510 Sep 202630 Jun 2029—Not yet due0
Royal ComplexZiscon Infra India LLPPM133000260186410 Sep 202631 May 203131 May 2031Not yet due0
Ruby HeightRamiz Sikandar Ahmad PatelPM13300026017944 Sep 202630 Aug 2029—Not yet due0
High Rise ApartmentHighrise Builders And DevelopersPM13300026017663 Sep 202631 Dec 202931 Dec 2029Not yet due0
Afra HeightInselmount Buildcon LLPPM133000260169831 Aug 202631 Dec 202731 Dec 2027Not yet due0
Leo Krista HeightsLeo Krista HomesPM133000260167027 Aug 202631 Dec 203031 Dec 2030Not yet due0
Usha GreensVidishabuildcon LLPPR13300026014787 Aug 202631 Dec 202931 Dec 2029Not yet due0
Usha GreensNavdeep RealtorsPR13300026014777 Aug 202631 Dec 202931 Dec 2029Not yet due0
Usha GreensPakshal Builders And DevlopersPR13300026014757 Aug 202631 Dec 2029—Not yet due0
Sai Swastik AnantaVenture ConstructionsPM133000260128423 Jul 202611 Feb 202911 Jun 2029Extended 4 mo0
Aayat ManzilI S A InfraPR133000260126220 Jul 202631 Dec 2032—Not yet due0
Everest HeightsOmnibuild Realty LLPPR133000260114713 Jul 202631 Dec 203230 Apr 2033Extended 4 mo0
Rangari HeightsAyesha ConstructionsPR13300026010183 Jul 202612 Jan 203012 May 2030Extended 4 mo0
Adelphi A and BLodha Developers LimitedPR133000260093124 Jun 202631 Mar 203131 Jul 2031Extended 4 mo0
Asgar HeightsIconic Builders & DevelopersPR133000260088622 Jun 202631 Dec 203430 Apr 2035Extended 4 mo0
Harsha Apartment Co-Operative Housing Society LimitedStonework Developers LLPPR133000260086519 Jun 202631 Dec 203130 Apr 2032Extended 4 mo0
Al Abbas Building No. 06Ayman Infra ConstructionsPR133000260079415 Jun 202631 Dec 2035—Not yet due0

Other talukas in Thane

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Macrotech Developers Limited17 projects
  2. Lodha Developers Limited13 projects
  3. Arihant Enterprises7 projects
  4. Shakti Realty6 projects
  5. Adrika Developers Private Limited4 projects
  6. Al Araaf Infra Private Limited4 projects
  7. Siyara Realty Private Limited4 projects
  8. Xrbia Warai Developers Private Limited4 projects
  9. Infini Developers3 projects
  10. Kgi Realty Private Limited3 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology