RERA projects in Ambarnath
1,594 projects under 1,679 MahaRERA registrations, registered 2017–2026. 42% have a completion date extended beyond the one promised.
Taluka
1,594RERA projects
1,679Registrationssome projects hold several
585Completion still due993 past their completion date, 22 marked completed
4 monthsMedian extension beyond promised date42% of registrations extended
89Regulatory caseson 24 projects
3,051Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 341 |
| 2018 | 136 |
| 2019 | 131 |
| 2020 | 74 |
| 2021 | 138 |
| 2022 | 177 |
| 2023 | 182 |
| 2024 | 126 |
| 2025 | 148 |
| 2026 | 125 |
Projects in Ambarnath
1,594 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Maa ShardaShreyas Enterprises And Construction | PR1330002602477 | 19 Oct 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Mangal Chhaya Co Operative Hsg Soc LtdShree Laxminarayan Constructions | PM1330002602480 | 19 Oct 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Shree Smaran HeightsPrime Homes | PR1330002602461 | 19 Oct 2026 | 31 Aug 2029 | — | Not yet due | 0 |
| Dnyan Mauli C.h.s.l.Maruti Construction Co | PM1330002602427 | 18 Oct 2026 | 28 Feb 2030 | — | Not yet due | 0 |
| La CasaFairway Realty Builders & Developers | PM1330002602347 | 16 Oct 2026 | 29 Dec 2029 | — | Not yet due | 0 |
| Navchetan Co-operative Housing Society LtdAbir Enterprises | PM1330002602370 | 16 Oct 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Jay Vijayshri Co. Op. Hsc. SocK S Builders & Developers | PM1330002602323 | 15 Oct 2026 | 31 Mar 2030 | — | Not yet due | 0 |
| Sakhi ResidencyAspire Builders | PR1330002602332 | 15 Oct 2026 | 1 Mar 2029 | — | Not yet due | 0 |
| Shreeji Landmark HillsShreejee Developers | PR1330002602324 | 15 Oct 2026 | 31 May 2029 | — | Not yet due | 0 |
| Shree Ambika ResidencyShree Ambika Enterprises | PR1330002602289 | 14 Oct 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Shree VastuM/s PA Developers | PR1330002602304 | 14 Oct 2026 | 30 Sep 2028 | — | Not yet due | 0 |
| M/s Kamlesh Co.Operative Housing Society Ltd.Kulvinder Infrastructure Private Limited | PR1330002602253 | 12 Oct 2026 | 31 May 2029 | 31 May 2029 | Not yet due | 0 |
| Verma ExoticaGrrs Nirman Private Limited | PR1330002602210 | 8 Oct 2026 | 30 Sep 2028 | 30 Sep 2028 | Not yet due | 0 |
| AltamountPV Ventures | PR1331012602180 | 7 Oct 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| KalpataruSuraj Builders | PR1330002602159 | 6 Oct 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Laxman ParadiseShree Ganesh Developers | PM1330002602148 | 5 Oct 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Panvelkar Daffodils-Plot No. 11,12,13Ameya Developers | PR1330002601956 | 17 Sep 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Infinity MeadowsInfinity Realty | PR1330002601926 | 15 Sep 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Mahavir HeritageMahavir Realty | PM1330002601924 | 15 Sep 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Gokul HeightsSairaj Developers | PR1330002601884 | 11 Sep 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Hari Shrushti Wing A Phase IIShrushti Creators | PM1330002601855 | 10 Sep 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Ishwar Jay Jay Shankara Co-Op. Housing Society Ltd.Ishwar Reality | PM1330002601833 | 8 Sep 2026 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Davakhar Sereno Phase III CDavakhar Infrastructure Private Limited | PR1332022601763 | 3 Sep 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Jankrishna HeightsJanki Developers | PR1330002601758 | 3 Sep 2026 | 31 May 2029 | 31 May 2029 | Not yet due | 0 |
| City Pride NxAbhishek Buildcon | PM1330002601687 | 27 Aug 2026 | 31 Mar 2030 | 31 Mar 2030 | Not yet due | 0 |
Other talukas in Thane
Most active promoters
By projects registered here, as named on MahaRERA.
- Mohan Lifespaces LLP12 projects
- Ishwar Reality9 projects
- Mohan Hardasmal Tharwani8 projects
- D A Construction7 projects
- Gulabrao Baburao Karanjule Patil7 projects
- Kgi Realty Private Limited7 projects
- Pramukh Developers7 projects
- Keyblue Realtors Private Limited6 projects
- Panvelkar Infrastructures Private Limited6 projects
- Raj Group6 projects
Data through20 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology