Skip to content
Mixed · 1 building · 4 unitsRERA PM1180002600699

Starview

Deedo IDDP-MSB-R5D4

Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.

Chembur, Mumbai Suburban 400071 · by Balan Realty Llp

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 4 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 8 Jun 2026, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1180002600699
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM11800026006998 Jun 202631 Dec 203030 Apr 2031Balan Realty LLPProject page
Documents28

1 document held by Deedo, 27 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardBALAN REALTY LLP PAN CARD.pdf · uploaded 17 Mar 2026Source
  • GSTIN DocumentGST BALAN REALTY LLP GST REG CERT..pdf · uploaded 17 Mar 2026Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 30 Mar 2026Source
  • OthersANNEXURE A OF ALL PARTNERS.pdf · uploaded 9 Apr 2026Source
  • Declaration Form BLEGAL TITLE REPORT - STARVIEW.pdf · uploaded 21 Apr 2026Source
  • OthersPROPERTY CARD.pdf · uploaded 7 May 2026Source
  • Declaration Form BPROPERTY CARD.pdf · uploaded 7 May 2026Source
Show all 28 documentsShow fewer documents

Legal

  • OthersANNEXURE A OF ALL PARTNERS.pdf · uploaded 11 May 2026Source

Migrated

  • Withdrawal Update Form 1FORM 1 ARCHITECT CERTIFICATE 30-06-2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 ENGINEER CERTIFICATE 30-06-2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 CA CERTIFICATE 30-06-2026.pdf · uploaded 21 Jul 2026Source

Planning Authority

  • DocumentMCGM_603142327-16-10-2018 04-15-26$_$BALAN REALTY LLP PAN CARD.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_1815894590-16-10-2018 04-24-23$_$DDP 2034.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_2391780_IOD_signed.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_2516316_FirstCC_signed.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_Provisional_Fire_NOC_Certificate.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_051701070215234199016.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_051701070215248363016.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_Provisional_Fire_NOC_Certificate.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_052103070215251612316.pdf · uploaded 14 Mar 2026Source
  • DocumentMCGM_051803070215251613916.pdf · uploaded 14 Mar 2026Source

Technical

  • DocumentBUILDING PLAN.pdf · uploaded 17 Mar 2026Source
  • DocumentANNEXURE A ORDER 50.pdf · uploaded 22 Apr 2026Source
  • OthersClarification letter.pdf · uploaded 12 May 2026Source
  • OthersCLARIFICATION REGARDING BANK UNITS.pdf · uploaded 12 May 2026Source

Technical (Architect)

  • DocumentFORM 1 ARCHITECT CERTIFICATE 30-06-2026.pdf · uploaded 21 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2 ENGINEER CERTIFICATE 30-06-2026.pdf · uploaded 21 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS NO. 339/3

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—16 units in all
Address
V.n. Purav MargPIN 400071
Village
Chembur, Kurla taluka
Land area for this project
1,281 sq m (13,791 sq ft)
Permissible built-up area
1,808 sq m (19,457 sq ft)
Sanctioned built-up area
1,808 sq m (19,457 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
17
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS NO. 339/3

Land as published on MahaRERA's project page

339/3

Boundaries

North
V N Purav Marg
South
Cts No 340
East
Cts No 339/2
West
Cts No 339/5 And 339/4

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

16 units registered

— · 16 units
TypeCarpet areaUnits
——16

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Chembur

All 125 projects in Chembur · Compare Starview with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology