9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects20
Registrations21some projects hold several
Completion still due147 past their date
Median extension4 months67% of registrations extended
Regulatory cases1on 1 project

9 in 10 registrations run late here

21 MahaRERA registrations in Lower Parel

2 not yet due12 extended, not yet due7 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Lower Parel

20 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sila TowerSila Offices Private LimiitedDue Apr 2032, extended 4 mo——
Embassy CitadelEquinox India Infraestate Limited, Spero Properties And Services Private LimitedDue Oct 2034, extended 4 mo——
Aetheria TowerP R EnterprisesDue Apr 2027, extended 4 mo——
Navkar OmniaR V Property Ventures LLPDue Apr 2028, extended 4 mo—1%
7 MahalaxmiRunwal Real Estates Private LimitedDue Jan 2035, extended 4 mo——
All 20 projects →
Lower Parel market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Nearby: other villages in Ward Gsouth

Most active promoters

  1. Macrotech Developers Limited2 projects
  2. Raheja Universal (Pvt.) Ltd2 projects
  3. Chintamani Construction Company1 project
  4. Equinox India Infraestate Limited, Spero Properties And Services Private Limited1 project
  5. Hatdia Builders Pvt Ltd1 project
  6. Lokhandwala Kataria Construction Private Limited1 project
  7. Lotus Enterprises1 project
  8. Mumbai Shelter Housing Development1 project
  9. Om Shanti City Development Co1 project
  10. P R Enterprises1 project

Lower Parel, in questions

How many projects in Lower Parel run late?

9 in 10 MahaRERA registrations (19 of 21): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Lower Parel by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology