Skip to content
Residential / Group Housing · 1 building · 52 unitsRERA P51800031635

Maple Heights

Deedo IDDP-MUM-D0P3

Completion was pushed back 1 year and 3 months to Jun 2026, and that date has passed too; no MahaRERA orders on record; 52% of its units are booked.

Byculla, Mumbai City 400011 · by Isd Infrastructure

Delivery1 yr 8 mo latePromised Mar 2025 · revised Jun 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales52% booked27 of 52 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year and 3 months to Jun 2026, and that date has passed too

  • This projectRegistered 3 Nov 2021, completion promised 7 Mar 2025, revised to 30 Jun 2026, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51800031635
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000316353 Nov 20217 Mar 202530 Jun 2026M/s ISD InfrastructureProject page
Documents85

2 documents held by Deedo, 83 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardISD INFRASTRUCTURE PAN CARD.pdf · uploaded 26 Oct 2021Source

Legal

  • Legal Title reportTitle Certificate Format A.pdf · uploaded 26 Oct 2021Source
  • Declaration Form BAffidavit Cum Declaration Form B Promoter.pdf · uploaded 26 Oct 2021Source
  • Declaration Form BForm-B Affidavit.pdf · uploaded 19 Mar 2025Source

Migrated

  • 1 PAN CardISD INFRASTRUCTURE PAN CARD.pdf · uploaded 26 Oct 2021Source
  • 1 Copy of the legal title reportTitle Certificate Format A.pdf · uploaded 26 Oct 2021Source
Show all 85 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesSelf Declaration-No Encumbrance.pdf · uploaded 26 Oct 2021Source
  • 1 Copy of Layout Approval (in case of layout)AMENDED Drawing.pdf · uploaded 26 Oct 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentIOD -Maple Heights-ISD.pdf · uploaded 26 Oct 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Kalapani.pdf · uploaded 26 Oct 2021Source
  • 1 Declaration about Commencement CertificateDeclaration Format D.pdf · uploaded 26 Oct 2021Source
  • 1 Declaration in FORM BAffidavit Cum Declaration Form B Promoter.pdf · uploaded 26 Oct 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 26 Oct 2021Source
  • 1 Proforma of Allotment letterLetter of Allotment.pdf · uploaded 26 Oct 2021Source
  • 2 Proforma of Allotment letterAgreement for Sale send by rera.pdf · uploaded 26 Oct 2021Source
  • 1 CERSAI detailsCERSAI Report and Undertaking.pdf · uploaded 15 Dec 2021Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold - Book Inventory Mapel Heights.pdf · uploaded 15 Dec 2021Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Inventory-MAPLE HEIGHTS.pdf · uploaded 11 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q1 2324.pdf · uploaded 7 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q2 2324.pdf · uploaded 7 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q3 2324.pdf · uploaded 7 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1Q4 2324.pdf · uploaded 7 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q1 2425.pdf · uploaded 7 Feb 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q2 2425.pdf · uploaded 7 Feb 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q3 2425.pdf · uploaded 7 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22.pdf · uploaded 7 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 7 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 7 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q4-21-22.pdf · uploaded 13 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2 Q4-22-23.pdf · uploaded 13 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q1-23-24.pdf · uploaded 13 Mar 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q2-23-24.pdf · uploaded 13 Mar 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q3-23-24.pdf · uploaded 13 Mar 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Q4-23-24.pdf · uploaded 13 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q1-24-25.pdf · uploaded 17 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q2-24-25.pdf · uploaded 17 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q3-24-25.pdf · uploaded 17 Mar 2025Source
  • 1 Declaration in FORM BForm-B Affidavit.pdf · uploaded 19 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q4 FY 21-22.pdf · uploaded 19 Mar 2025Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 FY 24-25.pdf · uploaded 19 Mar 2025Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 FY 24-25.pdf · uploaded 19 Mar 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q1 FY 24-25.pdf · uploaded 19 Mar 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q4 FY 23-24.pdf · uploaded 19 Mar 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 FY 23-24.pdf · uploaded 19 Mar 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 FY 23-24.pdf · uploaded 19 Mar 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q1 FY 23-24.pdf · uploaded 19 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q4 FY 22-23.pdf · uploaded 19 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Inventary Q3 24-25.pdf · uploaded 19 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 21-22.pdf · uploaded 19 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 22-23.pdf · uploaded 19 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 23-24.pdf · uploaded 19 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect-Q4 FY-2425.pdf · uploaded 4 Jun 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form -3 CA Q4-FY-2425.pdf · uploaded 4 Jun 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 -Engineer Q4-FY-2425.pdf · uploaded 4 Jun 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Revalidation issue letter.pdf · uploaded 4 Jun 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Inentory Q4-2024-25.pdf · uploaded 4 Jun 2025Source
  • 1 Declaration about Commencement CertificateCC Revalidation issue letter.pdf · uploaded 4 Jun 2025Source
  • Form 1FORM 1 Q4 24-25 Maple Heights.pdf · uploaded 25 Aug 2026Source
  • Form 2Form 2 Q4 24-25 Maple Heights.pdf · uploaded 25 Aug 2026Source
  • Form 3Form 3 Q4 24-25 Maple Heights.pdf · uploaded 25 Aug 2026Source
  • Disclosure of Sold and Booked InventoryInventory Q4 24-25 Maple Heights.pdf · uploaded 25 Aug 2026Source
  • Form 2A (FY 2024-2025)Form 2A 24-25 Maple Height New.pdf · uploaded 18 Sep 2026Source
  • Form 2A (FY 2025-2026)Form 2A 25-26 Maple Heights New.pdf · uploaded 18 Sep 2026Source

Technical

  • DocumentAMENDED Drawing.pdf · uploaded 26 Oct 2021Source
  • DocumentIOD -Maple Heights-ISD.pdf · uploaded 26 Oct 2021Source

Technical (Architect)

  • DocumentFORM 1 Q1 2324.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 1 Q2 2324.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 1 Q3 2324.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 1Q4 2324.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 1 Q1 2425.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 1 Q2 2425.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 1 Q3 2425.pdf · uploaded 7 Feb 2025Source
  • DocumentForm-1 Architect-Q4 FY-2425.pdf · uploaded 4 Jun 2025Source

Technical (Engineer)

  • DocumentForm 2 Q4-21-22.pdf · uploaded 13 Mar 2025Source
  • DocumentForm2 Q4-22-23.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 2 Q1-23-24.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 2 Q2-23-24.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 2 Q3-23-24.pdf · uploaded 13 Mar 2025Source
  • DocumentForm-2 Q4-23-24.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 2 Q1-24-25.pdf · uploaded 17 Mar 2025Source
  • DocumentForm 2 Q2-24-25.pdf · uploaded 17 Mar 2025Source
  • DocumentForm 2 Q3-24-25.pdf · uploaded 17 Mar 2025Source
  • DocumentForm 2 -Engineer Q4-FY-2425.pdf · uploaded 4 Jun 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 23/1840 Byculla Division

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK52 units in all
Address
23/1840 Byculla Division, Byculla Station Road, BycullaPIN 400011
Land area for this project
1,311 sq m (14,112 sq ft)
Permissible built-up area
4,248 sq m (45,723 sq ft)
Sanctioned built-up area
3,146 sq m (33,863 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

23/1840 Byculla Division

Land as published on MahaRERA's project page

23/1840 Byculla Division

Boundaries

North
Breadberry Mills
South
Ganesh Hari Pandurang Marg
East
Hara Mala Building
West
Khusnuma Apartment

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking52 units

27 of 52 units booked (52%), as the promoter reported to MahaRERA

1BHK · 41 units2BHK · 11 units
TypeCarpet areaUnitsBooked
1BHK36.61 sq m · 394 sq ft105
1BHK36.86 sq m · 397 sq ft116
1BHK37.32 sq m · 402 sq ft2011
2BHK50.96 sq m · 549 sq ft11
2BHK61.79 sq m · 665 sq ft104

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGajjar and Associates—
Chartered accountantNarendra G Dave—
EngineerSupcon Consultants—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Byculla

All 30 projects in Byculla · Compare Maple Heights with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology