Skip to content
Others · 1 building · 15 unitsRERA P53000031295

Anantam Complex

Deedo IDDP-KOL-GJEB

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Vadgaon Kasba (M Cl), Kolhapur 416112 · by Arvind Baburao Patil

Delivery1 yr 11 mo past duePromised Dec 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 15 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 15 Oct 2021, completion promised 31 Dec 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP53000031295
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5300003129515 Oct 202131 Dec 202431 Dec 2024Arvind Baburao PatilProject page
Documents24

1 document held by Deedo, 23 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 8 Sep 2021Source

Legal

  • Legal Title reportTitle Report.pdf · uploaded 8 Sep 2021Source
  • Legal Title reportSearch Report.pdf · uploaded 8 Sep 2021Source
  • Declaration Form BForm B.pdf · uploaded 8 Sep 2021Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 8 Sep 2021Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 8 Sep 2021Source
  • 2 Copy of the legal title reportSearch Report.pdf · uploaded 8 Sep 2021Source
Show all 24 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesDetails of Encumbrances.pdf · uploaded 8 Sep 2021Source
  • 2 Details of encumbrancesIndex 2.pdf · uploaded 8 Sep 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 8 Sep 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Sep 2021Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 8 Sep 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 8 Sep 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 8 Sep 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 8 Sep 2021Source
  • 1 Proforma of Allotment letterAllotmet letter .pdf · uploaded 8 Sep 2021Source
  • 2 Proforma of Allotment letterAgreement to sell.pdf · uploaded 8 Sep 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentOm constructions sanctioned plan.pdf · uploaded 15 Sep 2021Source
  • 1 Declaration about Commencement CertificateFormat D_0001.pdf · uploaded 15 Sep 2021Source

Technical

  • DocumentLayout.pdf · uploaded 8 Sep 2021Source
  • DocumentOm constructions sanctioned plan.pdf · uploaded 15 Sep 2021Source

Technical (Architect)

  • DocumentArchitect Certificate.pdf · uploaded 8 Sep 2021Source

Technical (Engineer)

  • DocumentEngineer Certificate.pdf · uploaded 8 Sep 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel C.S.No.745

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Office space, Shop15 units in all
Address
C.S.No.745, Near Thanekar Chowk, Peth VadgaonPIN 416112
Village
Vadgaon Kasba (M Cl), Hatkanangle taluka
Land area for this project
214 sq m (2,303 sq ft)
Permissible built-up area
676 sq m (7,273 sq ft)
Sanctioned built-up area
676 sq m (7,273 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

C.S.No.745

Land as published on MahaRERA's project page

C.S.No.745

Boundaries

North
Property Of Shri Irekar and Others
South
Property of Shri Thanekar
East
Property of Shri Uttam Balu Koli and Others
West
Government Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking15 units

0 of 15 units booked (0%), as the promoter reported to MahaRERA

1BHK · 4 unitsOffice space · 4 unitsShop · 7 units
TypeCarpet areaUnitsBooked
1BHK49.34 sq m · 531 sq ft10
1BHK49.34 sq m · 531 sq ft10
1BHK55.07 sq m · 593 sq ft10
1BHK55.07 sq m · 593 sq ft10
Office space8.41 sq m · 91 sq ft10
Office space15.81 sq m · 170 sq ft10
Office space53.1 sq m · 572 sq ft10
Office space62.19 sq m · 669 sq ft10
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop11.91 sq m · 128 sq ft10
Shop12.11 sq m · 130 sq ft10
Shop13.25 sq m · 143 sq ft10
Shop14.94 sq m · 161 sq ft10
Shop15.45 sq m · 166 sq ft10
Shop17.5 sq m · 188 sq ft10
Shop17.6 sq m · 189 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGharkul Constructions—
Chartered accountantSacchidanand & Co—
EngineerGharkul Constructions—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Vadgaon Kasba (M Cl)

All 11 projects in Vadgaon Kasba (M Cl) · Compare Anantam Complex with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology