MahaLaxmi Krushnangan
Deedo IDDP-KOL-NZ62Completion was pushed back 4 months, to Mar 2027; no MahaRERA orders on record; 0% of its units are booked.
Kolhapur (M Corp.), Kolhapur 416012 · by Rajshri Satish Kulkarni
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Mar 2027
- This projectRegistered 31 May 2024, completion promised 10 Nov 2026, revised to 10 Mar 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP53000056438
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P53000056438 | 31 May 2024 | 10 Nov 2026 | 10 Mar 2027 | Rajshri Satish Kulkarni | Project page |
Documents79
1 document held by Deedo, 78 filings listed on MahaRERA's project page
Finance
Legal
Show all 79 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommence certificate old_rotated.pdf · uploaded 20 Nov 2023Source
- 1 Declaration about Commencement CertificateCommence certificate declaration.pdf · uploaded 20 Nov 2023Source
- 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 20 Nov 2023Source
- 1 Proforma of Agreement for saleA to sale for Rera 21-11-2023-1.pdf · uploaded 23 Nov 2023Source
- 1 Deviation Report with respect to Allotment letterdeviation allotment new.pdf · uploaded 29 Nov 2023Source
- 1 Deviation Report with respect to model copy of Agreementmodel agreement dev.pdf · uploaded 29 Nov 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizationsintersterepnew.pdf · uploaded 12 Dec 2023Source
- 1 a Details of encumbrances concerned to Financeencrumbkrushnew.pdf · uploaded 13 Jan 2024Source
- 1 b Details of encumbrances concerned to Legalencrumbkrushnew.pdf · uploaded 13 Jan 2024Source
- 1 Copy of the legal title reportlegal title report krush new_11zon.pdf · uploaded 24 Jan 2024Source
- 1 CERSAI detailscersaimainpage_merged(1).pdf · uploaded 24 Jan 2024Source
- 1 Proforma of Allotment letterAllotment Letter-2(2).pdf · uploaded 24 Jan 2024Source
- 2 a Details of encumbrances concerned to Financeselfdecencrumbkrush.pdf · uploaded 3 Mar 2024Source
- 2 b Details of encumbrances concerned to Legalselfdecencrumbkrush.pdf · uploaded 3 Mar 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samekrishbankinfo.pdf · uploaded 3 Mar 2024Source
- 1 Other – LegalkrushannexureA.pdf · uploaded 29 Apr 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CAKrushlatest.pdf · uploaded 5 May 2024Source
- 1 PAN CardRajashriPAN.pdf · uploaded 16 May 2024Source
- 1 Other – Technicalkrushchange.pdf · uploaded 23 May 2024Source
- 1 Other – Financekrushaffidivat.pdf · uploaded 27 May 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)ACE Scanner_2024_10_16.pdf · uploaded 24 Oct 2024Source
- Withdrawal Update Form 1wagh form 1.pdf · uploaded 8 Jan 2026Source
- Withdrawal Update Form 2Shivdeep form2.pdf · uploaded 8 Jan 2026Source
- Withdrawal Update Form 3Form 3 Rajshri Kulkarni_compressed.pdf · uploaded 8 Jan 2026Source
- Withdrawal Update Form 1wagh form 1.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form1 Jan26.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Shivdeep form2.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form2 Jan26.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3 Rajshri Kulkarni_compressed.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Sai_Builders_Form_3_compressed.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form1 Jan26.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 2Form2QPR3.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 3Form3QPR3_compressed.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 1Form1 Jan26.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 1Form1 Jan26.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 1Form1 Jan26.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 1Form1 Jan26.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 1Form1 Jan26.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 2Form2QPR3.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 2Form2QPR3.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 2Form2QPR3.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 2Form2QPR3.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 2Form2QPR3.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 3Q3QPR22012026compressed.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 3Q3QPR22012026compressed.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 3Q3QPR22012026compressed.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 3Q3QPR22112025compressed.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 3Q3QPR19010226compressed.pdf · uploaded 15 Mar 2026Source
- Withdrawal Update Form 1Q4QPRFORM1.pdf · uploaded 5 May 2026Source
- Withdrawal Update Form 2Q4QPRFORM2.pdf · uploaded 5 May 2026Source
- Withdrawal Update Form 3Q4QPRFORM3.pdf · uploaded 5 May 2026Source
- Withdrawal Update Form 1Q4QPRFORM1.pdf · uploaded 12 Aug 2026Source
- Withdrawal Update Form 2Q4QPRFORM2.pdf · uploaded 12 Aug 2026Source
- Withdrawal Update Form 3Q4QPRFORM3.pdf · uploaded 12 Aug 2026Source
- Withdrawal Update Form 1Q1Arch2627.pdf · uploaded 11 Sep 2026Source
- Withdrawal Update Form 1Q1Arch2627.pdf · uploaded 11 Sep 2026Source
- Withdrawal Update Form 2Q1Eng2627.pdf · uploaded 11 Sep 2026Source
- Withdrawal Update Form 2Q1Eng2627.pdf · uploaded 11 Sep 2026Source
- Withdrawal Update Form 3Q1CA2627_compressed.pdf · uploaded 11 Sep 2026Source
- Withdrawal Update Form 3Q1CA2627_compressed.pdf · uploaded 11 Sep 2026Source
- Form 2A (FY 2024-2025)ACE Scanner_20260918.pdf · uploaded 23 Sep 2026Source
- Form 2A (FY 2025-2026)ACE Scanner_20260918.pdf · uploaded 23 Sep 2026Source
- Form 2A (FY 2026-2027)ACE Scanner_20260918.pdf · uploaded 23 Sep 2026Source
- Form 5 (FY 2024-2025)ACE Scanner_20260926(2).pdf · uploaded 23 Sep 2026Source
- Form 5 (FY 2025-2026)ACE Scanner_20260926(2).pdf · uploaded 28 Sep 2026Source
Technical
Technical (Architect)
- DocumentQ1Arch2627.pdf · uploaded 11 Sep 2026Source
Technical (Engineer)
- DocumentQ1Eng2627.pdf · uploaded 11 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel RS No 906 Plot no 1 A Ward Kolhapur
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, landowner unit34 units in all
- Address
- RS No 906 Plot no 1 A Ward Kolhapur 416012, RS No 906 Plot no 1 A ward, Deokar PanandPIN 416012
- Village
- Kolhapur (M Corp.), Karvir taluka
- Land area for this project
- 833 sq m (8,966 sq ft)
- Permissible built-up area
- 2,391 sq m (25,734 sq ft)
- Sanctioned built-up area
- 2,391 sq m (25,734 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
RS No 906 Plot no 1 A Ward Kolhapur 416012
Boundaries
- North
- 12 m road
- South
- 7 m roadplot 2
- East
- plot no 2 and plot no 3
- West
- open space
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking34 units
0 of 34 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 39.68 sq m · 427 sq ft | 1 | 0 |
| 1BHK | 53.26 sq m · 573 sq ft | 6 | 0 |
| 1BHK | 54.9 sq m · 591 sq ft | 8 | 0 |
| 2BHK | 81.73 sq m · 880 sq ft | 3 | 0 |
| 2BHK | 82.14 sq m · 884 sq ft | 3 | 0 |
| landowner unit | 53.26 sq m · 573 sq ft | 5 | 0 |
| landowner unit | 54.9 sq m · 591 sq ft | 4 | 0 |
| landowner unit | 81.73 sq m · 880 sq ft | 2 | 0 |
| landowner unit | 82.14 sq m · 884 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Girish P Wagh | — |
| Chartered accountant | Sachin K Sohani | — |
| Engineer | Shivdeep Kashid | — |
Source: MahaRERA project page. Contact details are not shown.