Mixed · 9 buildings · 65 unitsRERA P53000023414

Shree Dattakrupa

Deedo IDDP-KOL-Y0VT

Completion was pushed back 5 years and 1 month, to Dec 2028; no MahaRERA orders on record; 5% of its units are booked.

Chandgad, Kolhapur 416509 · by Monarch Builders & Developers

DeliveryExtended 5 yrs 1 moPromised Nov 2023 · now due Dec 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales5% booked3 of 65 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 5 years and 1 month, to Dec 2028

  • This projectRegistered 12 Dec 2019, completion promised 28 Nov 2023, revised to 31 Dec 2028.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

9 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP53000023414
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5300002341412 Dec 201928 Nov 202331 Dec 2028Monarch Builders & DevelopersProject page
Documents58

3 documents held by Deedo, 55 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN.pdf · uploaded 11 Nov 2019Source

Legal

  • OtherARCHITECTS CERTIFICATE FORM.pdf · uploaded 12 Nov 2019Source
  • Declaration Form Bform b.pdf · uploaded 12 Nov 2019Source
  • Legal Title reportLEGAL REPORT.pdf · uploaded 6 Dec 2019Source
  • Declaration Form BForm_B_Affidiviat_MBD.pdf · uploaded 18 Mar 2024Source
Show all 58 documentsShow fewer documents

Legal

  • Declaration Form Bform_b-2028.pdf · uploaded 12 Dec 2024Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 11 Nov 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS_CERTIFICATE-FORM 1 (1).pdf · uploaded 11 Nov 2019Source
  • 1 Details of encumbrancesDetails of encumbrances.pdf · uploaded 12 Nov 2019Source
  • 1 Copy of Layout Approval (in case of layout)layout1.pdf · uploaded 12 Nov 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentlayout1.pdf · uploaded 12 Nov 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentpermission.pdf · uploaded 12 Nov 2019Source
  • 1 Declaration in FORM Bform b.pdf · uploaded 12 Nov 2019Source
  • 1 OtherARCHITECTS CERTIFICATE FORM.pdf · uploaded 12 Nov 2019Source
  • 1 Copy of the legal title reportLEGAL REPORT.pdf · uploaded 6 Dec 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (2).pdf · uploaded 6 Dec 2019Source
  • 1 Proforma of Allotment letterSALE AGREEMENT PERFORMA.pdf · uploaded 6 Dec 2019Source
  • 2 Copy of Layout Approval (in case of layout)Chandgad_Plan_Bldg_B.pdf · uploaded 2 Jan 2023Source
  • 3 Copy of Layout Approval (in case of layout)Chandgad_Plan_Bldg_A.pdf · uploaded 2 Jan 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentkohlapur__parmission_New.pdf · uploaded 2 Jan 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentChandgad_Nagarpanchayt_parmission.pdf · uploaded 2 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate.pdf · uploaded 2 Jan 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Monarch Develpers Form 3.pdf · uploaded 2 Jan 2023Source
  • 2 Declaration in FORM BForm_B_Affidiviat_MBD.pdf · uploaded 18 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Mar 2020.pdf · uploaded 20 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Mar 2021.pdf · uploaded 20 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Mar 2022.pdf · uploaded 20 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Mar 2023.pdf · uploaded 20 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-1.pdf · uploaded 13 Apr 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 13 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHKITECT_CERTIFICATE_FORM_1.pdf · uploaded 6 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)30-06-2023.pdf · uploaded 6 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)30-09-2023.pdf · uploaded 6 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)31-12-2023.pdf · uploaded 6 Nov 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)31-03-2024.pdf · uploaded 6 Nov 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 24.pdf · uploaded 6 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 31-03-2024.pdf · uploaded 6 Nov 2024Source
  • 1 Declaration in FORM Bform_b-2028.pdf · uploaded 12 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 2019-2020.pdf · uploaded 12 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 2020-2021.pdf · uploaded 12 Dec 2024Source
  • 1 Disclosure of sold/ booked inventorySold_Inventory.pdf · uploaded 12 Dec 2024View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 2021-2022.pdf · uploaded 12 Dec 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 2022-2023.pdf · uploaded 12 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-2023.pdf · uploaded 12 Dec 2024Source

Technical

  • Documentlayout1.pdf · uploaded 12 Nov 2019Source
  • Documentlayout1.pdf · uploaded 12 Nov 2019Source
  • DocumentChandgad_Plan_Bldg_B.pdf · uploaded 2 Jan 2023Source
  • DocumentChandgad_Plan_Bldg_A.pdf · uploaded 2 Jan 2023Source
  • Documentkohlapur__parmission_New.pdf · uploaded 2 Jan 2023Source
  • DocumentChandgad_Nagarpanchayt_parmission.pdf · uploaded 2 Jan 2023Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 24 Sep 2024Source
  • DocumentARCHKITECT_CERTIFICATE_FORM_1.pdf · uploaded 6 Nov 2024Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 24 Sep 2024Source
  • DocumentForm 2.pdf · uploaded 6 Nov 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 881

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
2BHK, Office space, 1BHK65 units in all
Address
881, Changad, ChandgadPIN 416509
Village
Chandgad, Chandgad taluka
Land area for this project
1,211 sq m (13,032 sq ft)
Permissible built-up area
2,074 sq m (22,325 sq ft)
Sanctioned built-up area
2,074 sq m (22,325 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

881

Land as published on MahaRERA's project page

881

Boundaries

North
Adj CTS NO 879880
South
Adj CTS NO 882883
East
10 M Wide Road
West
3 M Wide Panand Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking65 units

3 of 65 units booked (5%), as the promoter reported to MahaRERA

2BHK · 10 unitsOffice space · 2 units1BHK · 53 units
BuildingTypeCarpet areaUnitsBooked
A Wing2BHK49.75 sq m · 536 sq ft21
A Wing2BHK59.55 sq m · 641 sq ft81
A WingOffice space120.77 sq m · 1,300 sq ft10
A WingOffice space130 sq m · 1,399 sq ft10
B2 Wing1BHK38.65 sq m · 416 sq ft60
B2 Wing1BHK44.18 sq m · 476 sq ft70
B2 Wing1BHK44.56 sq m · 480 sq ft70
B2 Wing1BHK47.29 sq m · 509 sq ft60
Show all 12 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Bi Wing1BHK34.65 sq m · 373 sq ft70
Bi Wing1BHK36.43 sq m · 392 sq ft71
Bi Wing1BHK37.1 sq m · 399 sq ft60
Bi Wing1BHK39.29 sq m · 423 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMeenakshi Regade—
ArchitectMs Narkars And Associates—
Chartered accountantSuresh Oak And Associates—
EngineerVinay Patil—
EngineerV N Kamat—
OtherSiddhesh Construction—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology