Yash Govinda Build Infra Llp
Deedo IDDD-KAPXOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 71 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ramkrishna NiketanP51700015764 | Naupada | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | +71 mo* |
| PadmanabhP51700016741 | Naupada | Certificate Signed | 24 Oct 2023 | 24 Oct 2023 | On date |
Yash Govinda Build Infra Llp, in questions
Does Yash Govinda Build Infra Llp finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 71 mo late. Across Maharashtra, 73% kept their date.
How many projects has Yash Govinda Build Infra Llp registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Yash Govinda Build Infra Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.