Xrbia Developers Ltd
Deedo IDDD-6DSROf 5 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late.
Delivery record
5 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Listed as an NCLT insolvency project | First CityListed as NCLT project: First City | Not on record |
| Listed as an NCLT insolvency project | Express City Khopoli Woods New LonavalaListed as NCLT project: EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA - PH -4 | Not on record |
| Listed as an NCLT insolvency project | Express City Khopoli Woods New LonavalaListed as NCLT project: EXPRESS CITY /KHOPOLI WOODS/NEW LONAVALA - PH 2 | Not on record |
| Listed as an NCLT insolvency project | Express City Khopoli Woods New LonavalaListed as NCLT project: EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1 | Not on record |
| Listed as an NCLT insolvency project | Express City Khopoli Woods New LonavalaListed as NCLT project: EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| First CityP52100005244 | Kharpudi Kh | Certificate Signed | 28 Aug 2023 | 28 Aug 2023 | +39 mo* |
| Express City Khopoli Woods New LonavalaP52000007138 | Madap | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | +44 mo* |
| Express City Khopoli Woods New LonavalaP52000007610 | Madap | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +83 mo* |
| Express City Khopoli Woods New LonavalaP52000008195 | Madap | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | +44 mo* |
| Express City Khopoli Woods New LonavalaP52000011789 | Madap | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | +44 mo* |
Xrbia Developers Ltd, in questions
Does Xrbia Developers Ltd finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.
How many projects has Xrbia Developers Ltd registered with MahaRERA?
2 projects under 5 MahaRERA registrations; 0 completed on MahaRERA.
Does Xrbia Developers Ltd have MahaRERA regulatory cases?
5 regulatory cases name its registrations, including an insolvency (NCLT) case.