Company or firm · first RERA registration 2017

Xrbia Developers Ltd

Deedo IDDD-6DSR

Of 5 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late.

Projects25 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay44 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases5includes insolvency

Delivery record

5 of 5 registrations with dates moved or missed their RERA date · months late against the original promise

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
First CityP52100005244Kharpudi KhCertificate Signed28 Aug 202328 Aug 2023+39 mo*
Express City Khopoli Woods New LonavalaP52000007138MadapCertificate Signed30 Mar 202330 Mar 2023+44 mo*
Express City Khopoli Woods New LonavalaP52000007610MadapCertificate Signed31 Dec 201930 Dec 2021+83 mo*
Express City Khopoli Woods New LonavalaP52000008195MadapCertificate Signed30 Mar 202330 Mar 2023+44 mo*
Express City Khopoli Woods New LonavalaP52000011789MadapCertificate Signed30 Mar 202330 Mar 2023+44 mo*

Xrbia Developers Ltd, in questions

Does Xrbia Developers Ltd finish projects on time?

Of 5 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.

How many projects has Xrbia Developers Ltd registered with MahaRERA?

2 projects under 5 MahaRERA registrations; 0 completed on MahaRERA.

Does Xrbia Developers Ltd have MahaRERA regulatory cases?

5 regulatory cases name its registrations, including an insolvency (NCLT) case.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology