Windows Co-operative Housing Society Ltd
Deedo IDDD-THC0Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Window Cooperative Housing Society Limited 222/2P52100005822 | Sus | Certificate Signed | 31 Dec 2019 | 31 Dec 2026 | +84 mo |
| Window Cooperative Housing Society Limited 131/1P52100005823 | Sus | Certificate Signed | 31 Jul 2027 | 30 Nov 2027 | +4 mo |
Windows Co-operative Housing Society Ltd, in questions
Does Windows Co-operative Housing Society Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.
How many projects has Windows Co-operative Housing Society Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Windows Co-operative Housing Society Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.