Skip to content
Company or firm · first RERA registration 2017

Windows Co-operative Housing Society Ltd

Deedo IDDD-THC0

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay44 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Window Cooperative Housing Society Limited 222/2P52100005822SusCertificate Signed31 Dec 201931 Dec 2026+84 mo
Window Cooperative Housing Society Limited 131/1P52100005823SusCertificate Signed31 Jul 202730 Nov 2027+4 mo

Windows Co-operative Housing Society Ltd, in questions

Does Windows Co-operative Housing Society Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.

How many projects has Windows Co-operative Housing Society Ltd registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Windows Co-operative Housing Society Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology