Vraj Realty
Deedo IDDD-V3EVOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 35 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Virat GreenwoodsP52000017471 | Pashane | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Virat GreenwoodsP52000022839 | Pashane | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
| Virat Greenwoods Wing EP52000029781 | Pashane | Certificate Signed | 31 Dec 2023 | 30 Dec 2024 | +35 mo* |
| Virat Greenwoods Wing B & DPM1270002501372 | Pashane | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Vraj Realty, in questions
Does Vraj Realty finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vraj Realty registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Vraj Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.