Skip to content
Company or firm · first RERA registration 2018

Vraj Realty

Deedo IDDD-V3EV

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 35 mo late.

Projects34 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay35 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Virat GreenwoodsP52000017471PashaneCertificate Signed30 Dec 202230 Dec 2022On date
Virat GreenwoodsP52000022839PashaneCertificate Signed30 Dec 202330 Dec 2023+35 mo*
Virat Greenwoods Wing EP52000029781PashaneCertificate Signed31 Dec 202330 Dec 2024+35 mo*
Virat Greenwoods Wing B & DPM1270002501372PashaneCertificate Signed31 Dec 202930 Apr 2030+4 mo

Vraj Realty, in questions

Does Vraj Realty finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vraj Realty registered with MahaRERA?

3 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.

Does Vraj Realty have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology