Vinod Premchand Chandwani
Deedo IDDD-12P8Of 16 registrations whose promised date has arrived, 13 kept it (81%). The rest ran a median 18 mo late.
Delivery record
3 of 16 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 16 registrations
16 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rose MansionP52100000173 | Punawale | Certificate Signed | 13 Dec 2020 | 13 Dec 2020 | On date |
| Silverland ResidencyP52100000190 | Ravet | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| DayalheightsP52100000191 | Pimpale Saudagar | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Royale Rahadki Greens New PhaseP52100000194 | Pimpale Saudagar | Certificate Signed | 30 Nov 2020 | 30 Nov 2020 | On date |
| Stkanwarrampalaciophase1P52100000276 | Chikhali Bk. | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Rose E MeharP52100000330 | Pimpale Saudagar | Certificate Signed | 30 Jun 2019 | 29 Dec 2020 | +18 mo |
| Stkanwarrampalaciophase2P52100000386 | Chikhali Bk. | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| G K MallP52100001188 | Pimpale Saudagar | Certificate Signed | 31 Jul 2019 | 31 Jul 2019 | On date |
| Rose AsterP52100018281 | Punawale | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
| Silverland ResidencyP52100019540 | Ravet | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| AryavatP52100021492 | Ravet | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| AriseP52100024704 | Punawale | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Dwarka Sai Wonder Phase 2 G WingP52100026971 | Pimpale Saudagar | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| Silverland ResidencyP52100027060 | Ravet | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| AllureP52100029341 | Ravet | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| Dwarka HeightsP52100031038 | Pimpale Saudagar | Certificate Signed | 15 Dec 2025 | 15 Dec 2025 | +11 mo* |
Show all 16 registrationsShow fewer
Vinod Premchand Chandwani, in questions
Does Vinod Premchand Chandwani finish projects on time?
Of 16 MahaRERA registrations whose promised completion date has arrived, 13 kept it (81%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vinod Premchand Chandwani registered with MahaRERA?
14 projects under 16 MahaRERA registrations; 14 completed on MahaRERA.
Does Vinod Premchand Chandwani have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.