Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 6 mo late.

Projects44 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay6 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shubh SrushtiP51700010469Badlapur (M Cl)Certificate Signed31 Oct 201831 Oct 2018On date
Shubh Srushti Phase IIP51700022224KatrapCertificate Signed25 Dec 202325 Dec 2023+35 mo*
New Vanrai Parag ChsP51700056295KulgaonActive31 May 2026—+6 mo*
Shubh Shrushti LMPR1330002600322KatrapCertificate Signed31 Dec 202830 Apr 2029+4 mo

Vinayak Enterprises, in questions

Does Vinayak Enterprises finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vinayak Enterprises registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.

Does Vinayak Enterprises have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.