Vijay Shridhar Tawde
Deedo IDDD-TS2POf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 5 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shridhar ApartmentP52900026841 | Vabhave | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Inamdar PlazaP52900048009 | Vabhave | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
Vijay Shridhar Tawde, in questions
Does Vijay Shridhar Tawde finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vijay Shridhar Tawde registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Vijay Shridhar Tawde have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.