Vijay Associates (Wadhwa)

Company or firm · 3 projects · 4 MahaRERA registrations · 1 reported completed

Projects34 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases2MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Elite SolitaireP51700006610Thane (M Corp.)2017Not reported30 Dec 2021—On date
Elite Platina 19P51700008189Thane (M Corp.)2017Not reported30 Dec 2021—On date
Elite SolitaireP51700009882Thane (M Corp.)2017Not reported30 Dec 2021—On date
Elite Platina 20P51700010204Thane (M Corp.)2017Completed30 Dec 2021—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Elite SolitaireOn date
  • Elite Platina 19On date
  • Elite SolitaireOn date
  • Elite Platina 20On date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology