Vihang Enterprises

Company or firm · 8 projects · 8 MahaRERA registrations

Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vihangs VermontP51700001458Thane (M Corp.)2017Not reported30 Dec 2022—On date
vihang woodsP51700005038Thane2017Not reported30 Dec 2026—On date
Vihang HillsP51700007590Thane (M Corp.)2017Not reported31 Dec 2018—On date
Vihang Plaza - A CommecialP51700012432Thane2017Not reported30 Dec 2026—On date
Golden Hills B- 3P51700020730Thane (M Corp.)2019Not reported30 Dec 2024—On date
Nova D-1P51700032331Thane (M Corp.)2021Not reported30 Dec 202830 Dec 2028On date
OrisPR1332022502040Bhayandarpada2026Not reported31 Dec 2032—On date
OpusPR1333032601879Bhayandarpada2026Not reported30 Sep 2032—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vihangs VermontOn date
  • vihang woodsOn date
  • Vihang HillsOn date
  • Vihang Plaza - A CommecialOn date
  • Golden Hills B- 3On date
  • Nova D-1On date
  • OrisOn date
  • OpusOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology