Vighnaharta Enterprises
Deedo IDDD-70T7Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 59 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vighnaharta ArcadeP51700017711 | Badlapur | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | +59 mo* |
| Lambodara PalaceP51700018977 | Badlapur | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | +71 mo* |
| Nav RushikeshP51700021294 | Ambarnath (R) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | +59 mo* |
Vighnaharta Enterprises, in questions
Does Vighnaharta Enterprises finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 59 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vighnaharta Enterprises registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Vighnaharta Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.