Venkatesh Laxmi Developers
Deedo IDDD-F1J6Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 42 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Suo motu order | Fortune Plaza Phase IISuo motu order: Secretary, MahaRERA Versus Venkatesh Laxmi Developers (Suo Motu Case No. 149 of 2020) dated 27 Feb 2020 | 6 Mar 2020 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Fortune Plaza Phase IIP52100009565 | Kharadi | Certificate Signed | 31 Dec 2018 | 30 Jun 2022 | +42 mo |
Venkatesh Laxmi Developers, in questions
Does Venkatesh Laxmi Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.
How many projects has Venkatesh Laxmi Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Venkatesh Laxmi Developers have MahaRERA regulatory cases?
1 regulatory case name its registrations.