Fortune Plaza Phase II
Completion date passedKharadi, Pune 411014 |Promoter: Venkatesh Laxmi Developers
Project summary
As registered with MahaRERA
MahaRERA's search listing gives this project's name, promoter and location only.
Location
Coordinates as published by MahaRERA
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 3 years and 6 months
The latest completion date on record passed 4 years and 4 months ago.
- Registered
- 22 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 30 Jun 2022
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100009565 | 22 Aug 2017 | 31 Dec 2018 | 30 Jun 2022 | Venkatesh Laxmi Developers | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Suo motu order6 Mar 2020Matched by RERA number
Suo motu order: Secretary, MahaRERA Versus Venkatesh Laxmi Developers (Suo Motu Case No. 149 of 2020) dated 27 Feb 2020
Source: MahaRERA regulatory lists and orders, checked against each RERA number.