Deedo IDDD-MHTVOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
None of 4 registrations with dates has moved or missed its RERA date
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| ARV NewtownP52100002738 | Pisoli | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| ARV Newtown Phase IIP52100015904 | Pisoli | Certificate Signed | 24 Dec 2025 | 24 Dec 2025 | On date |
| ARV NewtownP52100027214 | Pisoli | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| ARV NewtownPR1263032602727 | Pisoli | Not on record | 31 Dec 2034 | — | On date |
Vedant Infracon, in questions
Does Vedant Infracon finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Vedant Infracon registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Vedant Infracon have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.