Vaibhavlaxmi Builders And Developers

Company or firm · 8 projects · 9 MahaRERA registrations

Projects89 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%6 of 8 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Stella SapphireP51800003333Kurla2017Not reported31 Dec 2018—On date
Stella ResidencyP51800006691Kurla2017Not reported30 Apr 202129 Oct 2022+18 months
Stella SapphireP51800007545Kurla2017Not reported31 Dec 2019—On date
Green VistaP51800008487Kurla2017Not reported31 Dec 2018—On date
Templum HeightsP51800021056Kurla2019Not reported30 Dec 2024—On date
OlympusP51800022877Kurla2019Not reported30 Dec 2024—On date
Victoria 54P51800025304Kurla2020Not reported30 Dec 2025—On date
Royal StoneP51800029854Kurla2021Not reported31 Dec 202330 Nov 2024+11 months
Queens GloryP51800076971Chembur2024Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Stella SapphireOn date
  • Stella Residency+18 mo
  • Stella SapphireOn date
  • Green VistaOn date
  • Templum HeightsOn date
  • OlympusOn date
  • Victoria 54On date
  • Royal Stone+11 mo
  • Queens GloryOn date

Track record notes

  • 6 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Stella Residency (P51800006691).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology