Skip to content
Deedo home
Menu

Urban Realty

Company or firm · 9 projects · 9 MahaRERA registrations

Projects99 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date83%5 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Urban SolitaireP52100018555Peth2018Not reported1 Sep 202231 Aug 2023+11 months
ManakarnikaP52100024999Parvati2020Not reported30 Dec 2023—On date
ChaitanyashreeP52100025008Kothrud2020Not reported30 Dec 2023—On date
Vivek ApartmentsP52100029010Parvati2021Not reported31 Mar 2024—On date
9 EleganceP52100030395Parvati2021Not reported30 Jun 2024—On date
ShreedattaP52100051388Parvati2023Not reported30 Apr 2026—On date
SoumitraP52100076693Pune (M Corp.)2024Not reported31 Dec 2028—On date
NakshatraPR1260002500411Karve Nagar2025Not reported31 Dec 2028—On date
AshirwadPR1260002500485Karve Nagar2025Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Urban Solitaire+11 mo
  • ManakarnikaOn date
  • ChaitanyashreeOn date
  • Vivek ApartmentsOn date
  • 9 EleganceOn date
  • ShreedattaOn date
  • SoumitraOn date
  • NakshatraOn date
  • AshirwadOn date

Track record notes

  • 5 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 11 months, for Urban Solitaire (P52100018555).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology