Unique Shanti Realtors

Company or firm · 5 projects · 5 MahaRERA registrations

Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date25%1 of 4 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Unique Orbit-IP51700005412Mirabhayandar (M Corp.)2017Not reported30 Dec 2020—On date
Unique EstateP51700006459Mirabhayandar (M Corp.)2017Not reported30 Dec 20202 Mar 2023+27 months
Unique Orbit IIP51700009949Mirabhayandar (M Corp.)2017Not reported30 Dec 202030 Dec 2021+12 months
Unique Estate Wing EP51700026813Mirabhayandar (M Corp.)2020Not reported30 Jun 202331 Dec 2026+42 months
Unique Estate - IIP51700077619Mirabhayandar (M Corp.)2024Not reported30 Jun 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Unique Orbit-IOn date
  • Unique Estate+27 mo
  • Unique Orbit II+12 mo
  • Unique Estate Wing E+42 mo
  • Unique Estate - IIOn date

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 42 months, for Unique Estate Wing E (P51700026813).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology