Trimity Constructions
Deedo IDDD-9C1EOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 4 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Trimity AshwaP51700007057 | Thane (M Corp.) | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| HarmonyP51700022306 | Thane (M Corp.) | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Shri Shivanand ChsP51700024183 | Thane (M Corp.) | Certificate Signed | 30 Jun 2023 | 19 Aug 2024 | +14 mo |
| Asavari Co Op Hsg Soc LtdP51700045809 | Naupada | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | +1 mo* |
Trimity Constructions, in questions
Does Trimity Constructions finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Trimity Constructions registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Trimity Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.