Company or firm · first RERA registration 2017

Trimity Constructions

Deedo IDDD-9C1E

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 4 mo late.

Projects44 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Trimity AshwaP51700007057Thane (M Corp.)Certificate Signed31 Dec 201731 Dec 2017On date
HarmonyP51700022306Thane (M Corp.)Certificate Signed31 Dec 202630 Apr 2027+4 mo
Shri Shivanand ChsP51700024183Thane (M Corp.)Certificate Signed30 Jun 202319 Aug 2024+14 mo
Asavari Co Op Hsg Soc LtdP51700045809NaupadaCertificate Signed31 Oct 202631 Oct 2026+1 mo*

Trimity Constructions, in questions

Does Trimity Constructions finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Trimity Constructions registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Trimity Constructions have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology