Trillion Square Developers Llp
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Radha ResidencyP52000024079 | Wahal | 2020 | Certificate Signed | 30 Dec 2022 | 30 Dec 2023 | +12 months |
| Gana ResidencyP52000026641 | Ulawe | 2020 | Certificate Signed | 30 Jun 2023 | 31 Dec 2025 | +30 months |
| Trillion PrideP52000026747 | Ulawe | 2020 | Certificate Signed | 30 Dec 2023 | 31 Dec 2025 | +24 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 30 months, for Gana Residency (P52000026641).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology