Trident Developers
Deedo IDDD-86TJOf 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Trident AvenueP52000026574 | Ulawe | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Mountain SapphireP52000054446 | New Panvel | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Trident Developers, in questions
Does Trident Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Trident Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Trident Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.