The United Group Of Builders And Developers
Deedo IDDD-HW14Of 4 registrations whose promised date has arrived, 4 kept it (100%).
Delivery record
1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mrudagandhar Phase 1P52000000998 | Ambeghar | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | On date |
| United Galaxy Phase 4P52000001710 | Pen (M Cl) | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| ArumP52000025472 | Pen (M Cl) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Mrudagandhar Phase 2 Devashree E type BuildingP52000028928 | Ambeghar | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Mrudagandhar Phase 3 Rageshree D Type BuildingP52000079172 | Ambeghar | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
The United Group Of Builders And Developers, in questions
Does The United Group Of Builders And Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has The United Group Of Builders And Developers registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 4 completed on MahaRERA.
Does The United Group Of Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.