Company or firm · first RERA registration 2017

The Lifestile Realty

Deedo IDDD-26HX

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 23 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay23 mowhen late
First sales on record2registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Chowhan Residency/ AmaltasP52100004955UndriCertificate Signed31 Dec 201731 Dec 2017On date
Chowhan Residency Phase IIP52100050683UndriCertificate Signed31 Dec 202431 Dec 2025+23 mo*

The Lifestile Realty, in questions

Does The Lifestile Realty finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.

How many projects has The Lifestile Realty registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does The Lifestile Realty have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology