Tejas Enterprises
Deedo IDDD-PP0GOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tejas ParishmaP52000006095 | Ulawe | Certificate Signed | 31 Oct 2019 | 31 Oct 2019 | On date |
| Tejas EmeraldP52000009591 | Ulawe | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Tejas SparshP52000013995 | Ulawe | Certificate Signed | 30 Apr 2021 | 30 Oct 2022 | +18 mo |
Tejas Enterprises, in questions
Does Tejas Enterprises finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Tejas Enterprises registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Tejas Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
