Tapadia Infraprojects
Deedo IDDD-R3P7Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 69 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tapadia Estate - Phase IP51300016847 | Sailu | Certificate Signed | 30 Jun 2021 | 31 Mar 2027 | +69 mo |
Tapadia Infraprojects, in questions
Does Tapadia Infraprojects finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 69 mo late. Across Maharashtra, 73% kept their date.
How many projects has Tapadia Infraprojects registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Tapadia Infraprojects have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.