Synergy Properties
Deedo IDDD-9F3FOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bougain Villa - Cluster 3P52100009058 | Pasure | Certificate Signed | 31 Dec 2031 | 31 Dec 2031 | On date |
| Casuarina - Cluster C And DP52100010452 | Male | Certificate Signed | 1 Dec 2021 | 31 Dec 2028 | +84 mo |
| Bougain Villa - Cluster 1P52100011902 | Pasure | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
Synergy Properties, in questions
Does Synergy Properties finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.
How many projects has Synergy Properties registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Synergy Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.