Suyog Builders
Deedo IDDD-2R7BOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 47 mo late.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Suyog Space - Phase IP52100008633 | Wakad | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +47 mo* |
| Suyog Space - Phase IIP52100032138 | Wakad | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Suyog SadanP52100032390 | Pimple Nilakh | Completed | 30 Dec 2022 | 30 Dec 2022 | On date |
Suyog Builders, in questions
Does Suyog Builders finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Suyog Builders registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Suyog Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.