Individual promoter · first RERA registration 2017

Suresh Bhanwarlal Munot Jain

Deedo IDDD-EFEF

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 82 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay82 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rajbhav PalaceP50600012922Bhandara (M Cl)Certificate Signed31 Dec 201931 Dec 2019+82 mo*

Suresh Bhanwarlal Munot Jain, in questions

Does Suresh Bhanwarlal Munot Jain finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 82 mo late. Across Maharashtra, 73% kept their date.

How many projects has Suresh Bhanwarlal Munot Jain registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Suresh Bhanwarlal Munot Jain have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology