Surekha Tukaram Dudhe
Deedo IDDD-HXZROf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dudhe VitevariP52000007869 | Karanjade | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Sea RegencyP52000010351 | Ulawe | Certificate Signed | 30 Dec 2021 | 30 Dec 2022 | +12 mo |
| Sai NeevantP52000054139 | Karanjade | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Surekha Tukaram Dudhe, in questions
Does Surekha Tukaram Dudhe finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Surekha Tukaram Dudhe registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Surekha Tukaram Dudhe have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.