None of 3 registrations has reached its promised completion date yet.

Projects33 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AvionP52000051578DapoliCertificate Signed31 Dec 202931 Dec 2029On date
Sagar ViharP52000053568BokadviraCertificate Signed31 Dec 202931 Dec 2029On date
Surana GrandeP52000076659BokadviraCertificate Signed31 Dec 203030 Apr 2031+4 mo

Surana Commercials Private Limited, in questions

Does Surana Commercials Private Limited finish projects on time?

None of its 3 MahaRERA registrations has reached its promised completion date yet.

How many projects has Surana Commercials Private Limited registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Surana Commercials Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology