Sun Infrastructures Pvt. Ltd
Company or firm · 9 projects · 12 MahaRERA registrations · 1 reported completed
Also appears as SUN INFRASTRUCTURES PVT LTD
Projects912 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date58%7 of 12 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 5 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Suyojit One World Phase-II, Commercial And HospitalP51600002585 | Deolali (Cb) | 2017 | Not reported | 31 Mar 2019 | 31 Dec 2022 | +45 months |
| Suyojit One World Phase-I, Residential SectorP51600002632 | Deolali (Cb) | 2017 | Completed | 31 Mar 2019 | 30 Sep 2020 | +18 months |
| Suyojit Viridian Vallis-Phase 1-D1 Sector OtioP51600003685 | Nashik | 2017 | Not reported | 31 Mar 2021 | 31 Dec 2026 | +69 months |
| Suyojit Viridian VallisP51600019048 | Nashik | 2018 | Lapsed | 30 Mar 2023 | — | On date |
| Suyojit Viridian VallisP51600019052 | Nashik | 2018 | Not reported | 30 Dec 2023 | — | On date |
| Suyojit Viridian Vallis Phase-2, E-2 VivideP51600019066 | Nashik | 2018 | Lapsed | 30 Dec 2022 | — | On date |
| Suyojit Viridian VallisP51600019095 | Nashik | 2019 | Lapsed | 30 Jun 2023 | — | On date |
| Suyojit Viridian VallisP51600019106 | Nashik | 2019 | Lapsed | 30 Sep 2023 | — | On date |
| A Sector Suyojit Viridian VallisP51600019482 | Nashik | 2019 | Not reported | 31 Oct 2019 | — | On date |
| Suyojit Viridian Vallis Phase-III Sector G4 CommercialP51600031708 | Nashik (M Corp.) | 2021 | Not reported | 31 Dec 2023 | 31 Dec 2026 | +36 months |
| Suyojit Viridian Vallis Sector C And IP51600031936 | Nashik | 2021 | Not reported | 31 Mar 2023 | — | On date |
| Suyojit Viridian Vallis Phase-III Sector BP51600033475 | Nashik | 2022 | Not reported | 31 Jul 2024 | 31 Oct 2027 | +39 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 7 of 12 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 69 months, for Suyojit Viridian Vallis-Phase 1-D1 Sector Otio (P51600003685).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology