Deedo IDDD-WVXAOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sushrut Residency Phase IIP52100025563 | Narhe | Certificate Signed | 30 Apr 2024 | 30 Apr 2024 | +31 mo* |
| Vaijnath Residency 2P52100027327 | Narhe | Lapsed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
Sumeru Developers, in questions
Does Sumeru Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sumeru Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Sumeru Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.