Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 20 mo late.

Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay20 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Irasa GreensP51700005934DoholeCertificate Signed31 Dec 202730 Apr 2028+4 mo
Irasa ParkP51700010540MahimCertificate Signed31 Dec 202731 Dec 2027On date
Irasa ParkP99000015038MahimCertificate Signed30 Dec 202330 Dec 2023+35 mo*

Suburban Spaces LLP, in questions

Does Suburban Spaces LLP finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.

How many projects has Suburban Spaces LLP registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Suburban Spaces LLP have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology