Star Builders & Developers
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Star SheratonP99000012499 | Vasaivirar City (M Corp) | 2017 | Not reported | 31 May 2018 | 30 May 2019 | +12 months |
| Star Builders And DevelopersP99000005302 | Vasaivirar City (M Corp) | 2017 | Not reported | 31 Dec 2017 | — | On date |
| Star EraP99000018835 | Vasaivirar City (M Corp) | 2018 | Not reported | 30 Dec 2026 | — | On date |
| Star Signature City - Star PearlP99000031156 | Makane | 2021 | Not reported | 31 Dec 2026 | — | On date |
| Star SamruddhiP99000047822 | Chandrapada | 2022 | Not reported | 31 Dec 2027 | — | On date |
| Star Signature City-Star EmeraldP99000049637 | Makane | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Star Signature City - Star OpalP99000076877 | Makane | 2024 | Not reported | 30 Jun 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Star Sheraton (P99000012499).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology