Space Developers

Deedo IDDD-N6FV

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 31 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay31 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Radha Krishna ParkP51700023545KalwaCertificate Signed30 Jun 202730 Jun 2027On date
Radhakrishna Park Building No CP51700029596KalwaCertificate Signed30 Apr 202430 Apr 2024+31 mo*

Space Developers, in questions

Does Space Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 31 mo late. Across Maharashtra, 73% kept their date.

How many projects has Space Developers registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Space Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology