Company or firm · first RERA registration 2018

Space Builders & Developers

Deedo IDDD-NPM3

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record77registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shivom RegencyP52100014878BanerCertificate Signed31 Mar 202030 Mar 2022+24 mo
37 GrandstandP52100052752BanerCertificate Signed31 May 202730 Sep 2027+4 mo
Spectrum Commercial SpacesPC1260002502747BanerCertificate Signed31 Dec 202730 Apr 2028+4 mo

Space Builders & Developers, in questions

Does Space Builders & Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Space Builders & Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Space Builders & Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology