Solapur Infracon Pvt Ltd

Deedo IDDD-BG85

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 59 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay59 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Manmeet BlossomP52600002721Solapur (M Corp.)Certificate Signed30 Dec 202130 Dec 2021+59 mo*

Solapur Infracon Pvt Ltd, in questions

Does Solapur Infracon Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 59 mo late. Across Maharashtra, 73% kept their date.

How many projects has Solapur Infracon Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Solapur Infracon Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.